Plans P
6 July 2021 2022-08-14 20:01Plans P
Quiz Summary
0 of 30 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 30 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 30
1. Question
Plans: In order to prepare the project plan in a project, the project manager used the record company’s historical data, such as the types and number of human resources who took part in the previous similar projects.
However, for the stage plans, the project manager organized workshops with the team managers to estimate the resources required.
Is this appropriate, and why?
CorrectIncorrect -
Question 2 of 30
2. Question
Plans: During the ‘create the project plan’ activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 4 products. Therefore, the project manager decides to wait until the end of stage 3 to assess the risks to the project plan.
Is this an appropriate application of the plans theme, and why?
CorrectIncorrect -
Question 3 of 30
3. Question
Plans: When creating the stage plan, a project manager will also add the activities to the work packages as this is helpful for the team managers and they can better estimate the amount of work when the project manager hands out the work packages.
Is this appropriate, and why?
CorrectIncorrect -
Question 4 of 30
4. Question
Plans: Towards the end of an initiation stage, the executive advises the project manager that the programmed should be taken into account when planning the project.
Is the executive correct in asking this, and why?
CorrectIncorrect -
Question 5 of 30
5. Question
Plans: During the initiation stage, the project manager is creating the project plan. As part of which step of the PRINCE2’s recommended planning approach should this activity be carried out?
Producing the Logo on the home page and analyzing the target audiences of “Home Page”
CorrectIncorrect -
Question 6 of 30
6. Question
Plans: A change authority has been appointed for the project. During the development of the ‘Website’, a large number of changes were proposed to the design of the ‘Shop page’. Therefore, the change authority has decided to use the MoSCoW technique to prioritize changes based on the impact they will have on completing each stage on time.
Is this an appropriate application of the MoSCoW technique, and why?
CorrectIncorrect -
Question 7 of 30
7. Question
Plans: Here is a statement when planning a Music Album Project. Which step in PRINCE2’s recommended approach to planning would the following be first identified.
There is a dependency between ‘recorded sample songs’ and ‘signed contract’.
CorrectIncorrect -
Question 8 of 30
8. Question
Plans: The delivery of the software “Module A” has been split into two separate products: 1) ‘Tested Module A’ and 2) ‘Installed Module A’.
‘Tested Module A’ will be produced during stage 3, and the ‘Installed Module A’ will take place during stage 4. This will allow the project board to approve the plan for the Module A before the resources are committed to delivering the product.
Why is this an appropriate application of the plans theme to control the project?
CorrectIncorrect -
Question 9 of 30
9. Question
Plans: The project manager instructs the team manager to take corrective action, which will keep costs within the overall project and stage tolerances.
In which management product should the result of this event be recorded?
CorrectIncorrect -
Question 10 of 30
10. Question
Plans: In order to prepare the project plan in a project, the project manager used the record company’s historical data, such as the types and number of human resources who took part in the previous similar projects.
However, for the stage plans, the project manager organized workshops with the team managers to estimate the resources required.
Is this appropriate, and why?
CorrectIncorrect -
Question 11 of 30
11. Question
Plans: Here is a statement that is considered when planning a community Football Pitch project.
Which step in PRINCE2’s recommended approach to planning do they apply to?The project manager creates a work breakdown structure for a single product.
CorrectIncorrect -
Question 12 of 30
12. Question
Plans: When creating the stage plan, a project manager will also add the activities to the work packages as this is helpful for the team managers and they can better estimate the amount of work when the project manager hands out the work packages.
Is this appropriate, and why?
CorrectIncorrect -
Question 13 of 30
13. Question
Plans: There is a project to deliver a new website. During the initiation stage, the project manager of is creating the project plan. As part of which step of the PRINCE2’s recommended planning approach should this activity be carried out?
Identify what will make the ‘Website’ output acceptable to Sales Department so they will sign off on the project during the closing a project process.
CorrectIncorrect -
Question 14 of 30
14. Question
Plans: Here is a statement that is considered when planning a Music Album Project. Which step in PRINCE2’s recommended approach to planning do they apply to?
The Music Album Project will have four stages.
CorrectIncorrect -
Question 15 of 30
15. Question
Plans: Here is a statement that is considered when planning a Music Album Project. Which step in PRINCE2’s recommended approach to planning do they apply to?
A workshop will be held to identify the components that will make up the ‘recorded album’.
CorrectIncorrect -
Question 16 of 30
16. Question
Plans: The Executive tells the project manager during stage 2, that 70% of the Product A have been accomplished. The remainder will be accomplished within the agreed tolerances.
In which management product should the result of this event be recorded?
CorrectIncorrect -
Question 17 of 30
17. Question
Plans: During the initiation stage, the project manager is creating the project plan. As part of which step of the PRINCE2’s recommended planning approach should this activity be carried out?
CorrectIncorrect -
Question 18 of 30
18. Question
Plans: Here is a statement that is considered when planning a community Football Pitch project.
Which step in PRINCE2’s recommended approach to planning do they apply to?The project manager creates a diagram to show the sequence in which products will be developed.
CorrectIncorrect -
Question 19 of 30
19. Question
Plans: A project is approaching the end of stage 3. The project manager has invited the team managers involved in stage 4 to a workshop to draft the stage 4 plan. The project manager has asked the team managers, some of whom are external suppliers, to draft their team plans at the same time in order to verify that the stage plan is achievable.
Is this appropriate, and why?
CorrectIncorrect -
Question 20 of 30
20. Question
Plans: The project manager is instructed to produce a replacement plan for the current stage, to be presented to the project board at a meeting the following week.
In which management product should the result of this event be recorded?
CorrectIncorrect -
Question 21 of 30
21. Question
Plans: The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the ‘Product A’ has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.
Is the team manager’s response appropriate, and why?
CorrectIncorrect -
Question 22 of 30
22. Question
Plans: Here is a statement that is considered when planning a Music Album Project. Which step in PRINCE2’s recommended approach to planning do they apply to?
A workshop will be held to identify the components that will make up the ‘recorded album’.
CorrectIncorrect -
Question 23 of 30
23. Question
Plans: During the ‘create the project plan’ activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 4 products. Therefore, the project manager decides to wait until the end of stage 3 to assess the risks to the project plan.
Is this an appropriate application of the plans theme, and why?
CorrectIncorrect -
Question 24 of 30
24. Question
Plans: Here is a statement that is considered when planning a community Football Pitch project.
Which step in PRINCE2’s recommended approach to planning do they apply to?The project manager will consider the planning horizon
CorrectIncorrect -
Question 25 of 30
25. Question
Plans: Towards the end of an initiation stage, the executive advises the project manager that the programmed should be taken into account when planning the project.
Is the executive correct in asking this, and why?
CorrectIncorrect -
Question 26 of 30
26. Question
Plans: During the initiation stage, the project manager is creating the project plan. As part of which step of the PRINCE2’s recommended planning approach should this activity be carried out?
Determine that the ‘Home Page’ needs to be produced before the ‘About us’.
CorrectIncorrect -
Question 27 of 30
27. Question
Plans: A change authority has been appointed for the project. During the development of the ‘Website’, a large number of changes were proposed to the design of the ‘Shop page’. Therefore, the change authority has decided to use the MoSCoW technique to prioritize changes based on the impact they will have on completing each stage on time.
Is this an appropriate application of the MoSCoW technique, and why?
CorrectIncorrect -
Question 28 of 30
28. Question
Plans: A project is approaching the end of stage 3. The project manager has invited the team managers involved in stage 4 to a workshop to draft the stage 4 plan. The project manager has asked the team managers, some of whom are external suppliers, to draft their team plans at the same time in order to verify that the stage plan is achievable.
Is this appropriate, and why?
CorrectIncorrect -
Question 29 of 30
29. Question
Plans: The delivery of the software “Module A” has been split into two separate products: 1) ‘Tested Module A’ and 2) ‘Installed Module A’.
‘Tested Module A’ will be produced during stage 3, and the ‘Installed Module A’ will take place during stage 4. This will allow the project board to approve the plan for the Module A before the resources are committed to delivering the product.
Why is this an appropriate application of the plans theme to control the project?
CorrectIncorrect -
Question 30 of 30
30. Question
Plans: The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval.
The external team manager for the ‘Product A’ has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.Is the team manager’s response appropriate, and why?
CorrectIncorrect