Change P
6 July 2021 2022-08-14 20:00Change P
Quiz Summary
0 of 31 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 31 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 31
1. Question
Change: During stage 3, the ‘artwork’ for the music album has been completed. However, it does not fully meet the quality criteria requested by the singer and in the documented product description. The cost of corrective action will be €500 and will delay the project by a week. The team manager has discussed this issue with the graphic designer and the singer. It has been agreed that the ‘artwork’ is good enough and will be used as it is.
Is this an appropriate approach to controlling change, and why?
-
Question 2 of 31
2. Question
Change: The project manager wanted the stage to stay within budget and decided to choose a lower quality fence than what was specified in the security fence product description but that still met the quality requirements. As this issue is in his delegation limits, the project manager decided to manage it informally and record it in the daily log.
Is this an appropriate approach to controlling change, and why?
-
Question 3 of 31
3. Question
Change: During stage 3, the ‘artwork’ for the music album has been completed. However, it does not fully meet the quality criteria requested by the singer and in the documented product description. The cost of corrective action will be €500 and will delay the project by a week. The team manager has discussed this issue with the graphic designer and the singer. It has been agreed that the ‘artwork’ is good enough and will be used as it is.
Is this an appropriate approach to controlling change, and why?
-
Question 4 of 31
4. Question
Change: The executive of the “Website Development” Project is also a member of the project board for two other projects and is very busy. As a result, during the initiation stage, the executive has appointed another person to carry out both their business assurance role and the role of change authority for minor and medium severity issues.
Is this appropriate, and why?
-
Question 5 of 31
5. Question
Change: The project’s change control approach states that PRINCE2’s recommended issue and change control procedure will be used. The senior user has requested that a new set of marketing materials has to be introduced to support the launch of the “Website”. The senior user has suggested that this should be managed informally.
Where should the project manager record the issue, and why?
-
Question 6 of 31
6. Question
Change: The change control approach defines how products should be controlled and protected during the project. The approval of the ‘Logo design’ was planned to take place during stage 3. At the end of the stage, the configuration item record shows that the ‘Logo design’ have been approved. However, the project manager decides to request an audit of the product as well.
Is this appropriate, and why?
-
Question 7 of 31
7. Question
Change: During the Initiation Process, it is decided that Configuration item records will be created and maintained for all products in the projects: Mailing List, , Brochure.
In which management product should this be recorded?
-
Question 8 of 31
8. Question
Change: At the end of stage 2, the executive and senior user decided to add a new product to the scope of stage 3 and increase the project budget by £10,000 to cover the cost. This amount is sufficient to cover the cost and this change request (issue) will be managed using the recommended issue and change control procedure. However, after the executive notices that stage 3 has a cost tolerance of £12,000, the executive decided to use this money instead.
-
Question 9 of 31
9. Question
Change: The project manager has agreed with the building contractor on a drainage system for the community Football Pitch project. In the middle of the project, the project manager receives a letter from the building contractor mentioning that the drainage system’s price has increased. So they have to replace the system with another cheaper system or increase the contract price.
Here is an action being taken in response to this issue. Which role should be responsible for carrying this action out?Decide if the new cheaper drainage system meets the requirements
-
Question 10 of 31
10. Question
Change: During stage 3, the ‘artwork’ for the music album has been completed. However, it does not fully meet the quality criteria requested by the singer and in the documented product description. The cost of corrective action will be €500 and will delay the project by a week. The team manager has discussed this issue with the graphic designer and the singer. It has been agreed that the ‘artwork’ is good enough and will be used as it is.
Is this an appropriate approach to controlling change, and why?
-
Question 11 of 31
11. Question
Change: A request has been received from a user to change the design of the “Homepage” in the website project. The user has suggested that the number of visitors will be reduced if this change is not implemented.
Who should decide whether implementing the proposed changes to the “Homepage” will impact the achievement of the predicted visitors numbers?
-
Question 12 of 31
12. Question
Change: During the initiation stage, while planning the project, two members of the project support team argue about how to tailor the change principle and what are the minimum management products.
One of them believes that the project needs an issue register, change control approach as the minimum management product to comply with PRINCE2.
Is this appropriate for them to believe this, and why?
-
Question 13 of 31
13. Question
Change: The launch event for a new music album is planned to be held at a local hotel. A month before the event, the hotel unexpectedly has to close. Another venue is available, but it is double the cost of the original venue.
Here is an action being taken in response to the loss of venue.Which role (A-E) should be responsible for carrying them out?
Decide whether the impact on the project benefits of using an alternative venue, is acceptable.
-
Question 14 of 31
14. Question
Change: The project’s change control approach states that PRINCE2’s recommended issue and change control procedure will be used. The senior user has requested that a new set of marketing materials has to be introduced to support the launch of the “Website”. The senior user has suggested that this should be managed informally.
Where should the project manager record the issue, and why?
-
Question 15 of 31
15. Question
Change: A request has been received from a user to change the design of the “Homepage” in the website project. The user has suggested that the number of visitors will be reduced if this change is not implemented.
Who should provide information on the current status of the “Homepage”, to assist with the ‘capture and examine issues and risks’ activity?
-
Question 16 of 31
16. Question
Change: A request has been received from a user to change the design of the “Homepage” in the website project. The user has suggested that the number of visitors will be reduced if this change is not implemented.
Who should assess the impact of the requested change to the “Homepage”?
-
Question 17 of 31
17. Question
Change: The project manager has agreed with the building contractor on a drainage system for the community Football Pitch project. In the middle of the project, the project manager receives a letter from the building contractor mentioning that the drainage system’s price has increased. So they have to replace the system with another cheaper system or increase the contract price.
Here is an action being taken in response to this issue.Which role should be responsible for carrying this action out?: Send the issue to the change authority
-
Question 18 of 31
18. Question
Change: At the end of stage 3, the following products are shown as ‘approved’: ‘Shop page’, ‘Logo design’.
In which management product should this be recorded?
-
Question 19 of 31
19. Question
Change: The launch event for a new music album is planned to be held at a local hotel. A month before the event, the hotel unexpectedly has to close. Another venue is available, but it is double the cost of the original venue.
Here is an action being taken in response to the loss of venue. Which role (A-E) should be responsible for carrying them out?
Manage the issue and, if approved, arrange the alternative venue.
-
Question 20 of 31
20. Question
Change: The Sales Manager would like to change the graphical style of the Website to be inline with the new marketing standards. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 5 days and cost $1,300. The stage 3 cost tolerance of $1,500 has not been used. The change budget of $800 has not been used.
Which option describes how this change should be funded?
-
Question 21 of 31
21. Question
Change: The “Logo design” will be run two weeks later than originally planned, but this will not affect the end date of the stage or project.
In which management product should this be recorded?
-
Question 22 of 31
22. Question
Change: The project manager wanted the stage to stay within budget and decided to choose a lower quality fence than what was specified in the security fence product description but that still met the quality requirements. As this issue is in his delegation limits, the project manager decided to manage it informally and record it in the daily log.
Is this an appropriate approach to controlling change, and why?
-
Question 23 of 31
23. Question
Change: The launch event for a new music album is planned to be held at a local hotel. A month before the event, the hotel unexpectedly has to close. Another venue is available, but it is double the cost of the original venue.
Here is an action being taken in response to the loss of venue. Which role (A-E) should be responsible for carrying them out?
Obtain authority (secure funding) for an increase in the change budget to cover the cost of re-planning the launch event.
-
Question 24 of 31
24. Question
Change: The executive of the “Website Development” Project is also a member of the project board for two other projects and is very busy. As a result, during the initiation stage, the executive has appointed another person to carry out both their business assurance role and the role of change authority for minor and medium severity issues.
Is this appropriate, and why?
-
Question 25 of 31
25. Question
Change: The project manager has agreed with the building contractor on a drainage system for the community Football Pitch project. In the middle of the project, the project manager receives a letter from the building contractor mentioning that the drainage system’s price has increased. So they have to replace the system with another cheaper system or increase the contract price.
Here is an action being taken in response to this issue. Which role should be responsible for carrying this action out?Maintain the issue register and document this issue
-
Question 26 of 31
26. Question
Change: At the end of stage 2, the executive and senior user decided to add a new product to the scope of stage 3 and increase the project budget by £10,000 to cover the cost. This amount is sufficient to cover the cost and this change request (issue) will be managed using the recommended issue and change control procedure. However, after the executive notices that stage 3 has a cost tolerance of £12,000, the executive decided to use this money instead.
Is this appropriate, and why?
-
Question 27 of 31
27. Question
Change: A request has been received from a user to change the design of the “Homepage” in the website project. The user has suggested that the number of visitors will be reduced if this change is not implemented.
Who should assess the impact of the requested change to the “Homepage”?
-
Question 28 of 31
28. Question
Change: The change control approach defines how products should be controlled and protected during the project. The approval of the ‘Logo design’ was planned to take place during stage 3. At the end of the stage, the configuration item record shows that the ‘Logo design’ have been approved. However, the project manager decides to request an audit of the product as well.
Is this appropriate, and why?
-
Question 29 of 31
29. Question
Change: The Sales Manager would like to change the graphical style of the Website to be inline with the new marketing standards. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 5 days and cost $1,300. The stage 3 cost tolerance of $1,500 has not been used. The change budget of $800 has not been used.
Which option describes how this change should be funded?
-
Question 30 of 31
30. Question
Change: During the initiation stage, while planning the project, two members of the project support team argue about how to tailor the change principle and what are the minimum management products.
One of them believes that the project needs an issue register, change control approach as the minimum management product to comply with PRINCE2.Is this appropriate for them to believe this, and why?
-
Question 31 of 31
31. Question
Change: At the end of stage 3, the following products are shown as ‘approved’: ‘Shop page’, ‘Logo design’.
In which management product should this be recorded?